Hawthorne Army Depot New Bomb Request for Information
Contact and place of performance
Ashley Korves
NV 89415
USA
The Army Contracting Command - Rock Island, on behalf of Headquarters, Joint Munitions Command is issuing a request for information notice to identify capable sources for two stormwater detention pond projects at Hawthorne Army Depot (HWAD) in Hawthorne, NV. The first project includes clean-up/rehabilitation of the stormwater dry detention ponds. The second project includes design and construction of stormwater deten...
View moreRESPONSES: Interested vendors are invited to indicate their interest by providing the U.S. Government with the following information no later than 0900 central on 14 October 2025:
This request for information post is for information and planning purposes only and shall not be construed as a Request for Proposal or as an obligation on the part of the U.S. Government. The U.S. Government does not intend to award a contract on the basis of this request for information post or otherwise pay for information received.
Industry responses to this request for information post will not represent binding offers, and the U.S. Government cannot accept an industry response to form a binding contract. The U.S. Government intends to use any information submitted in response to this request to determine a path forward for meeting the described requirements.
In order to be eligible for contracts with the U.S. Government, Contractors must be registered in the System for Award Management (SAM) database prior to award, during performance, and through final payment of any contract resulting from a planned solicitation for these items. Contractors may obtain information on SAM registration by visiting: https://www.acquistion.gov. All interested companies are highly encouraged to get registered in SAM immediately.
The U.S. Government will hold all information submitted in a confidential status. Response to this request for information shall be provided via email to John Fotos at [email protected] and Ashley Korves at [email protected]. Submit questions to contact Contract Specialist, Ashley Korves, via email at [email protected].
ATTACHMENTS:
The Army Contracting Command - Rock Island, on behalf of Headquarters, Joint Munitions Command, issued this Special Notice to identify capable sources for two stormwater management projects at Hawthorne Army Depot in Hawthorne, Nevada. This requirement, identified under solicitation number W519TC-25-I-HWAD, is classified under NAICS 237990, Other Heavy and Civil Engineering Construction, and PSC C1PZ, Architect and Engineering- Construction: Other Non-Building Facilities. There is no set-aside for this opportunity, designated by the acronym and explanation NONE.
The scope of work is divided into two primary projects intended to run concurrently to minimize the movement of material and equipment. The first project involves the rehabilitation of stormwater controls at the New Bomb open burn/open detonation demilitarization site, requiring the clearance of silt and material deposited by flood events. Due to the nature of the site, the presence of unexploded ordnance must be considered during the cleanup of ponds and spillways. The second project requires the design and construction of new stormwater controls capable of withstanding a 500-year flood event and containing a 100-year event. On-site storage is available for aggregate and transient materials intended for reuse in the construction of ponds and spillways.
Interested vendors must submit a capability summary, subcontractor information, a Rough Order of Magnitude for each statement of work, and feedback on contract type and timeline efficiencies. Responses are due by 0900 Central on October 13, 2025, and should be directed to Ashley Korves. Documentation for this notice includes six attachments consisting of statements of work for cleanup and design-build tasks, geotechnical investigation reports, maps of clearance areas, and hydrological data.